Basement: Painting works in progress - Jul 2022
Basement: sinages works under progress - Jul 2022
Basement: Driveway marking and sinages work under progress - Jul 2022
Block A: QA certification of flats completed & painting works in progress at common areas - Jul 2022
Block D: QA certification of flats completed & painting works in progress at common areas - Jul 2022
Block F: QA certification & painting works in progress in common area - Jul 2022
Blocks E & F: QA certification & painting works in progress in common area - Jul 2022
Block S: Flat painting works in progress - Jul 2022
Badminton court area - Jul 2022
Podium side View: Block R and S - Painting works in progress - Jul 2022
Podium side View: Block Q - Flats painting works in progress - Jul 2022
Podium side View: Blocks F & G view - Jul 2022
Block G: QA certification of flats in progress and common area finishes QA de-snagging works in progress - Jul 2022
Southside Block View - Jul 2022
Southside Block View - Jul 2022
Southside Blocks View - Jul 2022
H Block View: QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022
Amphitheater View - Jul 2022
P Block View: QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022
N Block View: QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022
J Block View: QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022
K Blocks View: QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022
Northside Blocks View - Jul 2022
Northside Blocks View - Jul 2022
Southside Driveway - Jul 2022
Southside Driveway - Jul 2022
Westside L Block: QA certification of flats in progress and common area finishes QA de-snagging works in progress - Jul 2022
Westside M Block View: Block M - QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022
Westside Driveway - Jul 2022
Northside Driveway - Jul 2022
Eastside Driveway - Jul 2022
Entrance View: Block B - Flat painting works in progress - Jul 2022
Entrance View: Block C - Jul 2022
Entrance View: Block C - QA certification of flats completed and common area finishes QA de-snagging works in progress - Jul 2022